Avenue A, WWTP Road construction to move forward

By Chris Swick
October 07, 2015

The Avenue A and Wastewater Treatment Plant Road projects were both delayed slightly last week as construction had to wait for AT&T to move their lines out of the way.

“They are finally now clear,” Jeff Woodward, McPherson City Public Works Director, said. “The pavement is removed on those two projects and now the storm sewer installation can start on those two projects.”

As for the third project, the replacement of the west sewer trunk line, that was able to progress...

“[The contractor] was able to complete about 200 feet of 24-inch pipe and two of the manholes,” Woodward said. “Which is about seven percent.”

You can keep up with the various projects in the city through their Facebook page, McPherson Road Construction and Conditions.