Public Works Update

By KBBE News
April 10, 2017

Public Works Projects Approved

We have two repairs that need to be completed.  The needed repairs are at 1333 and 1345 Terrace Ct.. 

McPherson County to construct concrete parking in their existing parking lot at the Law Enforcement Center. 

We have 315' of Avenue "D", in the 100 block, that needs to be patched.  

Update on the Centennial Drive Sewer Project 

The Contractor was rained out on Tuesday last week.  To date we have installed 6,100' of sewer main, 22 manholes, and the project is 55% complete.

Anna Street 

We no more than got started with the alley sewer that runs parallel to Barber and Myers between Anna and Loomis when we discovered a design error.  To improve sewer reliability in this area, we need to lower the new main below the existing.  This will require us to take the new sewer line east to North High Drive to tie it in.  The Contractor brought a second crew to complete the alley sewer which he has now removed and taken to another job while the redesign is being accomplished.

Update on Centennial Drive Widening Project:

There was no progress on the Centennial Drive Widening Project again this week.  The mill and overlay may be accomplished in the first part of May.