Maxwell and Avenue Intersection will be closed Monday, June 5th. The closure is due to construction on the Avenue A 10’ sidewalk project.

According to Public Works

  To date, 1,000' of Storm sewer has been installed.

 Excavation for the retaining wall under the railroad tracks continues.  

Sidewalk, starting at Deerfield Street 150' to the west has been placed.

Approximately 50% Electrical conduit work is completed.  

Scheduled to place sidewalk and close Maxwell next week.  

Subgrade work continues from Maxwell to the Railroad bridge. 

Turkey Creek Drive is back open.

Click Here for a picture tour of the construction. 

http://midkansasonline.com/gallery/?school=News%20Gallery&team=Public%20Works&game=Avenue%20A%20Sidewalk