Public Works Report Nov. 13

By KBBE News
November 13, 2017

Here’s the McPherson Public Works Report from the Nov. 13 City Commission meeting:

Street Department: Patching on Carrie Street

Motion to approve patching in the 300 and 400 block of Carrie Street for a cost not to exceed $4,597.70 for materials only.

We have put together an estimate to patch two areas on Carrie Street.  One patch in the 300 block and one patch in the 400 block.  Total estimate for two patches is for $4,597.70 for materials only.

Street Department: Stop Sign Request at Penn and Canterbury

Motion to approve installing a stop sign on Canterbury at Penn Drive.

We received a request to install a yield sign at the intersection of Penn Drive on Canterbury. This intersection does not have the stopping sight distance required for a yield sign, therefore a stop sign is warranted.  

Street Department: Stop Sign Request at Grimes Street on Oaklane Drive

Motion to approve installing a stop sign on Oaklane Drive at Grimes Street.

We received a request to install a stop sign on Oaklane Drive at Grimes Street.  This intersection does not have adequate stopping sight distance required, therefore a stop sign is warranted.  

2018 Flag Schedule

Motion to approve the 2018 Flag Schedule as presented.

Attached is the proposed 2018 flag schedule.  We would like to put the flags up on the last working day before the event/holiday and take them down the first working day after the event/holiday to reduce overtime. 

Update on the Flory Ditch Construction Project (Phase I)

Work continued on the Flory Ditch Project (Phase I).  The wall is completed.   Placing of the apron is scheduled for early next week.  Final clean up and seeding should be accomplished in the next couple of weeks.  