Barnstormers/Premier Subdivision construction project update Jan. 8, 2018

By KBBE News
January 08, 2018

Here’s an update on the Barnstormers/Premier Subdivision construction project as of Jan. 8, 2018:

No grading work was completed in Barnstormers/Premier Subdivisions this past week.  However, good progress was made on the sanitary sewer.  The sanitary sewer main was completed in Barnstormers last week, leaving only the service risers to be completed.  Work is also expected to begin on the storm sewer this week.   