Construction updates May 7

By KBBE News
May 07, 2018

Update on the Barnstormers-Premier Subdivisions Project

The rain delayed the project last week.  BPU continues to work on the installation of water and electric in Barnstormers.   

Update on the North Front Street Project

Work was finished on North Front Street (McDonald's to Champlin Street) and the street was opened to unrestricted traffic.  

Update on the Avenue "A"/Centennial Drive 10' Sidewalk

Rain delayed the project this week.   The Cox Communication and AT&T conflicts discovered after the contractor started have now been cleared and out of the way of construction.  Last Monday they placed the sidewalk from the creek north to Avenue A. Approximately 3/4 of the sidewalk base is completed between the creek east to Centennial Drive, along the south side of KMU is completed and is scheduled to be placed today.    The dirt work is essentially complete from Deerfield to Clubhouse Drive.  Forming continued on the top slab and outside walls of the RCB. 