Construction Update June 11

By KBBE News
June 11, 2018

Update on the Avenue "A"/Centennial Drive 10' Sidewalk

Great progress was made this past week on this project.  The sidewalk was placed from Avenue "A" to the creek near Walmart.  Excavation and base continued from the creek to South Front Street.  The wing walls were placed on the box culvert between the dog park and the KMU.   Areas on the south side of the walk at the east end of the project were seeded and mulched.  Light poles were placed along areas of the sidewalk that was finished, with the exception of the area from Thunderbird Street to Clubhouse Drive.  That area is scheduled to be completed this week.  

Update on the Barnstormers-Premier Subdivisions Project

Curb and gutter was placed on Eastlinks Court and one block of Curtiss.  Pavement was placed in part of Eastlinks Court cul-de-sac.  Placement of pavement will continue this week.  Great progress is being made on this project.  

Update on the Elm Street Drainage Improvements

The contractor should be to Marlin Street by the end of this week.  At that point, because AT&T does not have their line cut over to the new duct, the contractor will move off the job and does not know when they will return.  


Close