Construction Update July 9

By KBBE News
July 09, 2018

Update on the Avenue "A"/Centennial Drive 10' Sidewalk

All concrete should be placed by the end of this week.  No progress on the lighting system, due to a delay in receiving wiring.  The drainage pipe by the pedestrian bridge has been installed, and all bricks have been placed in the ADA ramps.

Update on Barnstormers-Premier Subdivisions Project

Curb and gutter is complete.  Pouring of the main line will begin this week.   

Update on the Elm Street Drainage Improvements

The contractor was not on site this past week but is scheduled to begin work today (Monday)