Construction Update October 9

By KBBE News
October 09, 2018

Update on Barnstormers-Premier Subdivisions Project

No work was accomplished this past week.  Paperwork to add additional drainage features to the Barnstormers/Premier Contract is in progress. 

Update on the Elm Street Drainage Improvements

Patching was completed in the Euclid/Elm intersection and the east half of Euclid this past week.  As soon as weather permits, the contractor will move to the west half of the Euclid block.  This project should be completed in the next three weeks.