City of McPherson announces Mill and Overlay schedule

By City of McPherson Public Works
June 19, 2014

The City of McPherson has contracted with APAC-Kansas, Inc. Shears Division, to perform the 2014 Mill and Overlay street project beginning Monday, June 23rd, 2014.

Street construction will begin on Monday, June 23rd and will be completed by July 3rd, 2014, weather permitting.

Streets included are:

Avenue A from Hickory Street to the Highway 81 Bypass

Champlin Street from North Front Street to the end of the road

Hulse Street from the concrete west of Northglen Street to Maxwell Street

Maple Street from the K and O railroad to Woodside Street

Oaklane Street from Grimes to Sonora Drive

During times of construction, residents are asked to please follow all traffic control instructions and signage.

There will be periods when only local traffic will be allowed in the construction zone.

During the last phase of construction (asphalt paving), no traffic will be allowed on the street.

People living in these areas will receive notification from APAC-Kansas, Inc. Shears Division prior to work beginning in their area.